For a small indie team, game development project management needs a short, repeatable routine: agree what the player should experience, order the work, limit what starts, check what finishes and make scope changes deliberately. Hold a weekly decision review, with a short call between reviews for blocked tasks. Keep both meetings tied to decisions someone can act on.
The backlog connects those decisions to production. Each item needs an owner, an observable acceptance criterion and any dependencies that could stop it moving.
Start with one playable promise
In this fictional Lantern Post example, the team is building a route puzzle. The player rotates path tiles, connects a delivery route and presses Send. The design intent is that players can recognise a usable route and understand the feedback when their route fails.
The slice contains one tutorial plus three test layouts. Keep that boundary visible above the backlog. It gives the programmer, artist and tester the same target, while preventing an attractive extra feature from quietly becoming essential.
Translate the promise into checks. Does Send evaluate the displayed route? Does its UI cue explain the result? Do elbow pieces meet cleanly at junctions? These questions produce work that can be accepted against evidence.
Make the next decision visible
This example backlog shows the slice at a weekly review. Its order expresses priority. A blocked first item stays visible while the team resolves its dependency.
| Order and item | Owner and status | Acceptance criterion | Dependencies and risk response |
|---|---|---|---|
| 1. LP-07 — route Send engineering | Programmer Blocked |
Send evaluates the displayed route correctly and shows the agreed success or failure cue across the tutorial and three test layouts. | Depends on confirmation of the layout schema version. The integrated slice also needs the separate LP-ART-07 visual check. Designer confirms the schema before engineering resumes, avoiding rework against changing data. |
| 2. LP-ART-07 — elbow art | Artist Ready for acceptance |
Export v2 has the agreed pivots and passes junction alignment checks in the target build. | No backlog dependency. Receiving programmer checks import settings. Misalignment returns to the artist with a marked screenshot. |
| 3. LP-QA-07 — route checks | Tester Waiting |
A valid route starts exactly one delivery, a broken route leaves Send unavailable and shows its first break with icon and text, and repeat taps during delivery have no effect. | Depends on LP-07, including its UI cue. Tester prepares cases now and runs them when the integrated build is available. |
| 4. LP-DATA-01 — session events | Analytics engineer In progress |
Sample session events contain stable player IDs and usable timestamps before D1 measurement begins. | No delivery dependency on LP-07. Analytics engineer investigates missing or inconsistent fields before the team interprets retention. |
Acceptance criteria describe each item’s required behaviour. A shared Definition of Done adds common completion standards, such as review, relevant checks and evidence attached to the named build. The November 2020 Scrum Guide describes an emergent, ordered Product Backlog and a Definition of Done that makes completion standards transparent. A small team can borrow those principles without claiming to practise formal Scrum.
Control starts and unblock finishes
At the weekly review, inspect the playable build, accept completed work and reorder what remains. Then agree what each person will pull next. Begin with one active item per person, adjusting only when the team has a clear reason. Waiting work should not conceal several half-finished tasks.
Keep the blocked-task call to ten minutes. For LP-07, ask which schema decision is missing, who owns it and when it will arrive. The producer records the owner and next check. If confirmation slips, bring that consequence to the decision review. Starting another gameplay feature would add work without resolving the blockage.
Hand over something the receiver can check
For the example art hand-off, the artist supplies elbow export v2 for build LP-slice-05, with pivot settings and junction-check results attached to LP-ART-07. The note names the receiving programmer and QA as the owner of the visual acceptance check.
The programmer imports the asset, then QA checks its placement in that build. If a junction fails, record the layout and orientation so the artist can reproduce it. Keep the item awaiting acceptance until the check passes. An uploaded file alone does not establish that the hand-off worked.
Once the schema version is confirmed, LP-07 can proceed. LP-QA-07 starts its execution checks when both route behaviour and the UI cue are present in an identified build.
Give new requests a recorded decision
Suppose someone proposes a daily challenge during this slice. The producer, acting as scope decision owner, defers it so LP-07’s scope and evidence stay intact. Record the example decision as: 24 November 2026, owner producer, consequence no daily challenge in this slice, next review 1 December 2026.
Revisit the request with the route-check results and validated session data. D1 measurement still needs a defined cohort and return window, which belong with mobile-game retention metrics. For this review, decide whether the new request deserves priority and what existing work would move to make room.